All Technology Relations for Offshore Windfarm, Burbo Bank, detailed design
Show all technology relations
Burbo Offshore Wind Farm is constructed at a water depth of 3.5-7.5 m on Burbo Flats in Liverpool Bay, 4 miles from the Sefton Coast line.
25 3.6 MW turbines
The wind farm consists of 25 Siemens 3.6 MW wind turbines connected to shore by 3 buried submarine cables. The foundation works is carried out by MT Højgaard as a subcontractor and Ramboll was chosen to carry out the detailed design of the turbine foundation structures.
Further information: see our media at our profile
Pile installation challenges
The foundation structures are monopiles with grouted transition pieces made ready for mounting of the WTG tower structures once installed. At most positions the monopiles were driven, however, for a few positions, where the pile tip is below bedrock level, the piles were driven and drilled. The foundation structure is a monopile with a grouted transition piece similar to the foundation structures installed by MT Højgaard at Horns Rev.
Cost-efficient design solution
The design was carried out as 25 individual foundation designs based on the actual site conditions at the individual positions, i.e. the actual soil profile and water depth at each location. In comparison with the tender design based on five standardized foundation types, the detailed design of the monopile and transition piece as well as the grouted joint included a number of design innovations and advanced analyses, which lead to an overall weight reduction as well as substantial savings on steel and grout material quality.
The services by Ramboll